Contract Duration
32 months
Contract Value
€533 million

It consists of the engineering, the procurement, the construction and testing and commissioning of a new combined cycle power plant of 1650 MW in Baghdad Iraq.

This Plant consists of 4 gas turbines 9FA-4 series, 4 HRSG’S, two air cooled condensers and all auxiliaries.

The Project will deliver 540 MW in Summer 2020, another 540 MW in November 2020 and 570 MW by February 2022.

Bismayah phase II and Bismayah phase III are the largest power plants ever awarded to a Greek Contractor.

Following the completion of Bismayah phase III , the Bismayah block of power plants will have a size of 4650 MW, which make it one of the largest power plants ever built in the world.