ΚΟΣΤΟΣ ΚΑΤΑΣΚΕΥΗΣ
473,511,992 €
ΠΕΡΙΟΔΟΣ ΚΑΤΑΣΚΕΥΗΣ
2016 - 2019
Engineering, procurement and construction of Section 2 and 3 of the TAP pipeline, which is a part of the pipeline system transporting gas from Azerbaijan to Western Europe.
The project includes approx. 360 km of HP steel pipeline 48” situated in Greece, between Kavala and Ieropigi (Greek-Albanian border), 14 block valve stations, 1 scraper trap station (launcher & receiver), installation of approx 720 km of HDPE conduit and fiber optical cable (FOC) along the entire length of the pipeline, Cathodic protection.