High Pressure Natural Gas Pipeline

FINAL BUDGET:
51.234.713,33 €
CONSTRUCTION PERIOD:
2012 - 2014

AGIOI THEODORI TO MEGALOPOLIS, GREECE.

The project includes the detailed engineering, material and equipment procurement and construction of the extension of the Greek Natural Gas Transmission System for the supply of the the PPC Power Plant in Megalopolis with natural gas.

The project consists of a 30” diameter steel pipe which starts from the existing station of DESFA (LVS U-7040) at Agioi Theodoroi heading west, passes the Corinth Canal with with the use of Horizontal Directional Drilling (HDD) and ends in the area of Examilia.

A 24’’ diameter steel pipe runs south from from Examilia to the PPC power plant in Megalopolis.

The total length of the projects pipeline is 158.940m.