Panagopoula Railway Tunnel

CONTRACT VALUE
€ 293.000.000
CONTRACT DURATION
06/2013 – current project

The project consisted mainly of the construction of the Panagopoula twin railway tunnel, the central access tunnel and the entrance and exit Cut&Cover.

The contract title was «Infrastructure works of the new railway in the section Rododafni – Psathopyrgos from K.P. 91+500 to K.P. 113+000 and Panagopoula tunnel».

The project was about the construction of two single line rail tunnels of 8.758m total length, central access tunnel of 549m length, entrance and exit Cut&Cover of 741m total length, as well as the construction of the connection tunnels between the two main tunnels every 500m.

The construction works were completed through a joint venture form and held out by three construction sites.

Search: