Design and construction of Sludge Drying Plant at Psyttalia Wastewater Treatment Plant

CONTRACT VALUE
€37 millions
CONTRACT DURATION
2006 - 2008

PSYTTALIA ISLAND, GREECE

The Unit consists of four parallel drying lines with rotating drums.

Each drying line has an evaporation capacity of 8,625KgH2O/h with a maximum capacity of 9,200KgH2O/h.

Nominal dehydration capacity at 4*250tnDS/day, with 20% – 32% DS sludge concentration.

The final product, the “dried sludge”, is collected in four storage silos.

 