Wastewater Treatment Plantin Psyttalia (Phase I)

CONTRACT VALUE
52.300.000€
CONTRACT DURATION
1987 - 1998

AKROKERAMOS & PSYTTALIA ISLAND, GREECE

Design, construction of pre-treatment works (lift pumping station with Archimedes screws, screening, and sand removal), primary sedimentation tanks, pre-thickening, post-thickening, digestion, gas holders, Sludge dewatering, instrumentation and SCADA.

Perform a test run, commissioning, 12-month operation. Plant capacity of 750,000m³/day with anticipation of one million m³/day for a three million inhabitants.